2.......... Project Information
2.3 Construction Programme and
Activities
2.5 Status of Environmental Licences,
Notification and Permits
3.......... Environmental Monitoring
Requirements
3.1 Construction Dust Monitoring
3.2 Construction Noise Monitoring
4.......... Implementation
Status of Environmental Mitigation Measures
5.......... Monitoring
Results
5.1 Construction Dust Monitoring
5.2 Regular Construction Noise
Monitoring
6.......... ENVIRONMENTAL
SITE INSPECTION AND AUDIT
7.......... Environmental Non-conformance
7.1 Summary of Monitoring Exceedances
7.2 Summary of Environmental
Non-Compliance
7.3 Summary of Environmental Complaints
7.4 Summary of Environmental Summon and
Successful Prosecutions
8.1 Construction Programme for the Next
Three Months
8.2 Key Issues for the Coming Month
8.3 Monitoring Schedule for the Coming
Month
9.......... ConclusionS AND
RECOMMENDATIONS
List of Tables
Table 2.1........... Construction
Activities in the reporting month
Table 2.2........... Contact Information of Key Personnel
Table 2.3........... Status of Environmental Licenses, Notifications and
Permits
Table 3.1........... Air Quality Monitoring
Equipment
Table 3.2........... Location of Construction
Dust Monitoring Station
Table 3.3........... Noise Monitoring Parameters, Frequency and Duration
Table 3.4........... Noise Monitoring
Equipment for Regular Noise Monitoring
Table 3.5........... Noise Monitoring Stations during Construction Phase
Table 3.6........... Noise Monitoring Parameters, Frequency and Duration
Table 4.1........... Status
of Required Submission under Environmental Permit
Table 5.1........... Summary of 24-hour TSP Monitoring Result in the
Reporting Period
Table 5.2........... Summary of 1-hour TSP Monitoring Result in the
Reporting Period
Table 5.3........... Summary of Construction Noise Monitoring Results in
the Reporting Period
Table 6.1........... Observations and Recommendations of Site Audit
Table 8.1........... Construction
Activities in the coming three months
List of Figures
Site Layout Plan |
|
Location of Air Quality Monitoring Station |
|
Locations of Noise Monitoring Station |
|
|
|
List
of Appendices
Construction Programme |
|
Project Organization Structure |
|
Implementation Schedule of Environmental Mitigation Measures |
|
Summary of Action and Limit Levels |
|
Calibration Certificates of Equipment |
|
EM&A Monitoring Schedules |
|
Air Quality Monitoring Results and their Graphical Presentations |
|
Noise Monitoring Results and their Graphical Presentations |
|
Event and Action Plan Cumulative Statistics on Complaints, Notification of Summons and
Successful Prosecutions |
|
Monthly Summary Waste Flow Table |
Central Kowloon Route
– Kai Tak West (CKR-KTW; Contract No. HY/2014/07) (hereafter called “the
Project”) covers part of the construction of the Central Kowloon Route (CKR).
The Project comprises
the follow works:
·
50x30m access
shaft with noise enclosure at Ma Tau Kok (MTK);
·
100m long
cut-and-cover (C&C) tunnel at MTK;
·
Demolition
and re-provisioning of MTK Public Pier;
·
160m long
underwater tunnel (UWT) (Stage 1);
·
210m long
UWT (Stage 2);
·
60m long
C&C tunnel at Kai Tak;
·
130m long
depressed road and 200m long underpass at Kai Tak;
·
390m long
underground tunnel ventilation adit at Kai Tak;
·
Seawall
demolition and construction of new landing steps; and
·
Barging
Point enclosure and conveyor system.
The EM&A programme commenced on 4 April 2018.The impact EM&A for the Project includes
air quality and noise monitoring.
This is the
thirty-third monthly EM&A Report presenting the EM&A works carried out
during the period between 1 and 31 December 2020. As informed by the
Contractor, major activities in the reporting period were:
Locations |
Site Activities |
Kai Tak |
·
Casting tunnel wall at underpass and ventilation adit; ·
Base slab and wall, roof slab construction at cut & cover,
underpass and depressed road; ·
Backfilling at Underpass and depressed road; ·
Removal of ELS at cut & cover, underpass and depressed
road; ·
Falsework erection at cut & cover, underpass and
depressed road. |
Ma Tau Kok |
·
TTM implementation; ·
Shotcreting at the Access Shaft; ·
Fresh water pipe installation works; ·
Constrcution of MTK east wall and traffic deck; ·
Paving blocks at Covered Walkway. |
Kowloon Bay |
·
Concrete packing between wailing and CPP Wall; ·
Roof slab and base slab construction ·
Waterproofing application; ·
ELS Removal. |
Barging Point |
·
Barging point operation (Spoil Disposal) ·
Preparation works for taking over Kai Tak Barging Facility1 |
Remark: 1.
Barging Point under
FEP-01/436/2012/F was handed over from MTRCL on 22 Dec 2020 and will be
operated in January 2021. |
Breaches of Action and Limit Levels for Air Quality
All 24-hour TSP result was below the Action and
Limit Levels at all monitoring locations in the reporting month.
All 1-hour TSP result was below the Action and
Limit Levels at all monitoring locations in the reporting month.
Breaches of Action and Limit Levels for Noise
One (1) noise-related complaint was received
in the reporting month. Based on the investigation result from finalized
investigation reports, proper implementation of mitigation measures for noise
conducted by the Contractor during restricted hours and comply with the
condition of valid Construction Noise Permit. Also, there is no non-compliance
recorded based on compliance check of PMEs. Therefore, one action level of
construction noise was triggered, and the investigation report was finalized on
17 December 2020.
Regular Noise Monitoring
No exceedance of Limit Level of noise was recorded in
the reporting month.
Complaint, Notification of Summons and Successful Prosecution
Two (2) complaints in air or noise (one
received by Gammon Construction Limited on 27 November 2020 and two same
complaints received by Gammon Construction Limited and 1823 Hotline on 2 and 4
December 2020 respectively which summarized as one for investigation) were
referred by the Contractor on 2, 8 and 9 December 2020. Those investigation
reports were finalized on 11 and 17 December 2020, respectively.
No notification of summons and successful prosecution were received in
the reporting month.
Reporting Changes
No report changes in the reporting period.
Future Key Issues
Key issues to be considered
in the next three months included:
Locations |
Site Activities |
Kai Tak |
·
Base slab and wall, roof slab construction at cut &
cover, underpass and depressed road; ·
Backfilling works and ELS removal at cut & cover, underpass
and depressed road; ·
Dismantle of working platform. |
Ma Tau Kok |
·
TTM implementation; ·
Pipe piling works for cut and cover tunnel east portion; ·
Fresh water pipe installation works; ·
Constrcution of traffic deck; ·
Demolition of Kowloon City Public Pier. |
Kowloon Bay |
·
Backfilling and ELS removal works; ·
Roof slab, base slab and wall construction; ·
Waterproofing application; ·
Preparation works for Stage 2 UWT. |
Barging Point |
·
Barging point operation (Spoil Disposal); ·
Demolition of Kai Tak Barging Point1. |
Remark: 1.
Kai Tak Barging Point
will be handed over to other parties at the end of February 2021. |
·
Section 1:
Introduction
·
Section 2:
Project Information
·
Section 3:
Environmental Monitoring Requirement
·
Section 4:
Implementation Status of Environmental Mitigation Measures
·
Section 5:
Monitoring Results
·
Section 6:
Environmental Site Inspection and Audit
·
Section 7: Environmental Non-conformance
·
Section 8:
Future Key Issues
·
Section 9:
Conclusions and Recommendations
(a) construction of approximately 160m long cut-and-cover tunnel and 370m
long underwater tunnel between the tunnel section at Ma Tau Kok
and the depressed road of the CKR within Kai Tak Development;
(b) reconstruction of the seawall at Ma Tau Kok
public pier, and the sloping seawall at the Former Kai Tak Airport Runway;
(c) construction of approximately 125m long depressed road and 200m
long underpass of the CKR within Kai Tak Development;
(d) construction of approximately 360m long underground tunnel
ventilation adit of the CKR;
(e) reconstruction of Kowloon City Ferry Pier Public Transport
Interchange; and
(f) other associated works.
Table 2.1 Construction Activities in the reporting month
Locations |
Site Activities |
Kai
Tak |
·
Casting tunnel wall at underpass and ventilation adit; ·
Base slab and wall, roof slab construction at cut &
cover, underpass and depressed road; ·
Backfilling at Underpass and depressed road; ·
Removal of ELS at cut & cover, underpass and depressed
road; ·
Falsework erection at cut & cover, underpass and
depressed road. |
Ma
Tau Kok |
·
TTM implementation; ·
Shotcreting at the Access Shaft; ·
Fresh water pipe installation works; ·
Constrcution of MTK east wall and traffic deck; ·
Paving blocks at Covered Walkway. |
Kowloon
Bay |
·
Concrete packing between wailing and CPP Wall; ·
Roof slab and base slab construction ·
Waterproofing application; ·
ELS Removal. |
Barging
Point |
·
Barging point operation (Spoil Disposal) ·
Preparation works for taking over Kai Tak Barging Facility1 |
Remark: 1.
Barging Point under
FEP-01/436/2012/F was handed over from MTRCL on 22 Dec 2020 and will be
operated in January 2021. |
Table 2.2 Contact Information of Key Personnel
Party |
Role |
Position |
Name |
Telephone |
Fax |
Arup-Mott
MacDonald Joint Venture |
Residential
Engineer (ER) |
Engineer’s
Representative |
Mr. Jeffrey
Lau |
2268 3640 |
2268 3954 |
ERM |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker |
Ms. Mandy To |
2271 3313 |
2723 5660 |
Gammon |
Contractor |
Contracts Manager |
Mr. Alan Yan |
2516 8823 |
2516 6260 |
Environmental Manager |
Ms Michelle Tang |
9267 8866 |
2516 6260 |
||
AECOM |
Contractor’s
Environmental Team (ET) |
ET Leader |
Mr. Y T Tang |
3922 9393 |
2317 7609 |
Table 2.3 Status of Environmental Licenses, Notifications and Permits
Permit / License No. / Notification/
Reference No. |
Valid Period |
Status |
Remarks |
|
From |
To |
|||
Further Environmental Permit |
||||
FEP-01/457/2013/C |
28 Feb 2018 |
End of Project |
Valid |
-- |
FEP-01/436/2012/F1 |
6 Apr 2020 |
End of Project |
Valid |
FEP
for Shatin to Central Link (Hung Hom – Admiralty
Section) - Kai Tak Barging Facility |
Wastewater Discharge License |
||||
WT00030290-2018 |
22 Mar 2018 |
31 May 2023 |
Valid |
Ma Tau Kok |
WT00030668-2018 |
27 Apr 2018 |
30 Apr 2023 |
Valid |
Site Office at
Kai Tak West |
WT00030358-2018 |
27 Apr 2018 |
30 Apr 2023 |
Valid |
Kai Tak West |
WT00030333-2018 |
27 Apr 2018 |
30 Apr 2023 |
Valid |
Barging Point
at Portions 4B & 4C |
WT00030330-2018 |
27 Apr 2018 |
30 Apr 2023 |
Valid |
Kowloon Bay |
Construction Noise Permit |
||||
GW-RE0709-20 |
27 Aug 2020 |
26 Feb 2021 |
Valid |
Barging Point Operation at
Kai Tak Barging Point |
GW-RE0891-20 |
5 Nov 2020 |
4 Feb 2021 |
Valid |
General Works at Ma Tau Kok |
GW-RE0874-20 |
20 Oct 2020 |
14 Apr 2021 |
Valid |
General Works at Kai Tak |
GW-RE0989-20 |
25 Nov 2020 |
20 May 2021 |
Valid |
ELS Removal at Stage 1 UWT |
GW-RE0761-20 |
1 Oct 2020 |
31 Mar 2021 |
Valid |
Kai Tak Haul Road |
Chemical
Waste Producer Registration |
||||
5118-247-G2347-47 |
30 Jan 2018 |
End of Project |
Valid |
-- |
5118-247-G2347-48 |
30 Jan 2018 |
End of Project |
Valid |
-- |
Marine Dumping Permit |
||||
EP/MD/21-038 |
8 Oct 2020 |
7 Apr 2021 |
Valid |
Sediments requiring Type 1
- Open Sea Disposal |
Billing Account for Construction
Waste Disposal |
||||
7029909 |
22 Jan 2018 |
End of Project |
Account Active |
-- |
7031949 |
27 Nov 2020 |
26 Feb 2021 |
Account renewed on 27 Nov 2020 |
Billing Account for Disposal of
Construction Waste (by vessels) |
Notification Under Air Pollution
Control (Construction Dust) Regulation |
||||
429442 |
5 Jan 2018 |
5 Jul 2025 |
Notified |
-- |
Remark: 1. Barging Point under FEP-01/436/2012/F was handed over from
MTRCL on 22 Dec 2020 and will be operated in January 2021. |
Monitoring Requirements
Monitoring Equipment
Table 3.1 Air Quality Monitoring Equipment
Tisch
Total Suspended Particulate Mass Flow Controlled High Volume Air Sampler |
|
Calibration
Kit (24-hour
TSP) |
TISCH
Environmental Orifice |
Portable
direct reading dust meter |
Sibata Digital Dust Monitor |
Monitoring Locations
Table 3.2 Location of Construction Dust Monitoring Station
Location |
Monitoring Station |
Description |
E-A14a
[1] |
Block
B of Merit Industrial Centre |
Rooftop
(13/F) |
[1] The air monitoring station
proposed in the EM&A Manual (i.e. Wyler Gardens with ID: E-A14) was not
available for impact dust monitoring, therefore impact monitoring was conducted
at E-A14a as an alternative which was agreed by the ER, IEC and EPD.
Monitoring
Methodology
(a)
The HVS
was installed in the vicinity of the air sensitive receivers. The following criteria were considered in the
installation of the HVS as far as practicable: -
(i)
A horizontal platform with
appropriate support to secure the sampler against gusty wind was provided.
(ii)
Two samplers should
not be placed less than 2m apart from each other;
(iii)
The distance between the HVS and
any obstacles, such as buildings, was at least twice the height that the
obstacle protrudes above the HVS.
(iv)
A minimum of 2 meters separation from
walls, parapets and penthouse for rooftop sampler.
(v)
A minimum of 2 meters separation
from any supporting structure, measured horizontally is required.
(vi)
No furnace or incinerator flues
nearby.
(vii)
Airflow around the sampler was
unrestricted.
(viii)
The sampler was located more than
20 meters from any dripline.
(ix)
Any wire fence and gate, required
to protect the sampler, did not obstruct the monitoring process.
(x)
Permission was obtained to set up
the samplers and access to the monitoring station.
(xi)
A secured supply of electricity
was obtained to operate the sampler.
(b)
Preparation
of Filter Papers
(i)
Glass fibre filters, G810 were
labelled and sufficient filters that were clean and without pinholes were
selected.
(ii)
All filters were equilibrated in
the conditioning environment for 24 hours before weighing. The conditioning
environment temperature was around 25 °C and not variable by more than ±3 °C;
the relative humidity (RH) was < 50% and not variable by more than ±5%. A
convenient working RH was 40%.
(iii)
All filter papers were prepared
and analysed by ALS Technichem (HK) Pty Ltd., which is a HOKLAS accredited
laboratory and has comprehensive quality assurance and
quality control programmes.
(c)
Field
Monitoring
(i)
The power
supply was checked to ensure the HVS works properly.
(ii)
The filter holder and the area
surrounding the filter were cleaned.
(iii)
The filter holder was removed by
loosening the four bolts and a new filter, with stamped number upward, on a
supporting screen was aligned carefully.
(iv)
The filter was properly aligned
on the screen so that the gasket formed an airtight seal on the outer edges of
the filter.
(v)
The swing bolts were fastened to
hold the filter holder down to the frame.
The pressure applied was sufficient to avoid air leakage at the edges.
(vi)
Then the shelter lid was closed
and was secured with the aluminium strip.
(vii)
The HVS was warmed-up for about 5
minutes to establish run-temperature conditions.
(viii)
A new flow rate record sheet was
set into the flow recorder.
(ix)
On site temperature and atmospheric
pressure readings were taken and the flow rate of the HVS was checked and
adjusted at around 1.3 m3/min, and complied with the range specified
in the EM&A Manual (i.e. 0.6-1.7 m3/min).
(x)
The programmable digital timer
was set for a sampling period of 24 hrs, and the starting time, weather
condition and the filter number were recorded.
(xi)
The initial elapsed time was
recorded.
(xii)
At the end of sampling, on site
temperature and atmospheric pressure readings were taken and the final flow
rate of the HVS was checked and recorded.
(xiii)
The final elapsed time was
recorded.
(xiv)
The sampled filter was removed
carefully and folded in half length so that only
surfaces with collected particulate matter were in contact.
(xv)
It was then placed in a clean
envelope and sealed.
(xvi)
All monitoring information was
recorded on a standard data sheet.
(xvii) Filters were then sent to ALS Technichem (HK) Pty Ltd. for analysis.
(d)
Maintenance
and Calibration
(i)
The HVS and its accessories were maintained in good working condition, such as
replacing motor brushes routinely and checking electrical wiring to ensure a
continuous power supply.
(ii)
HVSs were calibrated using
TE-5025A Calibration Kit upon installation and thereafter at bi-monthly
intervals.
(iii)
Calibration certificate of the TE-5025A Calibration Kit and the HVSs are provided in
Appendix E.
(a)
Measuring Procedures
The measuring procedures of the 1-hour dust meter
are in accordance with the Manufacturer’s Instruction Manual as follows:
(i)
Turn the power on.
(ii)
Close the air collecting opening cover.
(iii)
Push the “TIME SETTING” switch to [BG]
(iv)
Push “START/STOP”
switch to perform background measurement for 6 seconds.
(v)
Turn the knob at SENSI ADJ position to insert
the light scattering plate.
(vi)
Leave the equipment for 1 minute upon “SPAN
CHECK” is indicated in the display.
(vii)
Push “START/STOP” switch to perform automatic
sensitivity adjustment. This measurement takes 1 minute.
(viii)
Pull out the knob and return it to MEASURE
position.
(ix)
Push the “TIME SETTING” switch the time set
in the display to 3 hours.
(x)
Lower down the air collection opening cover.
(xi)
Push “START/STOP” switch to start
measurement.
(b)
Maintenance and
Calibration
(i)
The 1-hour TSP meter
was calibrated at 1-year intervals against a continuous particulate TEOM
Monitor, Series 1400ab. Calibration certificates of the Laser Dust Monitors are
provided in Appendix E.
Monitoring Schedule for the
Reporting Month
Monitoring Requirements
Table 3.3 Noise Monitoring Parameters, Frequency and Duration
Parameter and Duration |
Frequency |
30-mins
measurement at each monitoring station between 0700 and 1900 on normal
weekdays. Leq, L10 and L90
would be recorded. |
At least once per week |
Table 3.4 Noise Monitoring Equipment for Regular Noise Monitoring
B&K (Model No. 2250-L & 2238) |
|
Acoustic
Calibrator |
B&K (Model
No. CAL21) |
Monitoring Locations
Table 3.5 Noise Monitoring Stations during Construction Phase
Location |
Monitoring Station |
Description |
Measurement |
E-N12a [1] |
19 Hing Yan Street |
Rooftop (9/F) |
Façade |
E-N21a [1] |
Block B of Merit Industrial Centre |
Rooftop (13/F) |
Free field[2] |
Notes:
[1] The noise monitoring stations proposed in
the EM&A Manual (i.e. Grand Waterfront Tower 3 with ID: E-N12 and Hang Chien Court Block J with ID: E-N21) were not available for
impact noise monitoring, therefore impact monitoring was conducted at E-N12a
and E-N21a as an alternative which was
agreed by the ER, IEC and EPD.
[2] A
correction of +3 dB(A) was made to the free field measurements.
Monitoring
Parameters, Frequency and Duration
Table 3.6 Noise Monitoring Parameters, Frequency and Duration
Location |
Parameter and Duration |
Frequency |
E-N12a
and E-N21a |
30-mins measurement at each
monitoring station between 0700 and 1900 on normal weekdays. Leq, L10 and L90 would
be recorded. |
At
least once per week |
Monitoring Methodology
(a)
The sound level meter was set on
a tripod at a height of 1.2 m above the ground.
(b)
Façade measurement was made at
E-N12a.
(c)
Free field measurements was made
at monitoring location E-N21a. A correction of +3 dB(A) shall be made to the
free field measurements.
(d)
The battery condition was checked to ensure the correct
functioning of the meter.
(e)
Parameters such as frequency
weighting, the time weighting and the measurement time were set as follows:
(i)
frequency weighting
(ii)
time weighting: Fast
(iii)
time measurement: Leq(30-minutes) during non-restricted
hours i.e. 0700 – 1900 on normal weekdays.
(f)
Prior to and after each noise
measurement, the meter was calibrated using the acoustic calibrator for 94
dB(A) at 1000 Hz. If the difference in
the calibration level before and after measurement was more than 1 dB(A), the
measurement would be considered invalid and repeat of noise measurement would
be required after re-calibration or repair of the equipment.
(g)
During the monitoring period, the
Leq, L10 and L90
were recorded. In addition, site
conditions and noise sources were recorded on a standard record sheet.
(h)
Noise measurement was paused
during periods of high intrusive noise (e.g. dog barking, helicopter noise) if
possible. Observations were recorded when intrusive noise was unavoidable.
(i)
Noise monitoring was cancelled in
the presence of fog, rain, wind with a steady speed exceeding 5m/s, or wind
with gusts exceeding 10m/s.
(a)
The
microphone head of the sound level meter was cleaned with soft
cloth at regular intervals.
(b)
The meter
and calibrator were sent to the supplier or HOKLAS laboratory to check and
calibrate at yearly intervals.
(c)
Calibration
certificates of the sound level meters and acoustic calibrators are
provided in Appendix
E.
Monitoring Schedule for the
Reporting Month
Table 4.1 Status of Required Submission under Environmental Permit
EP Condition |
Submission |
Submission
Date |
Condition 3.4 of |
Monthly EM&A Report
for November 2020 |
14 December 2020 |
Table 5.1 Summary of 24-hour
TSP Monitoring Result in the Reporting Period
ID |
Average (mg/m3) |
Range (mg/m3) |
Action Level (mg/m3) |
Limit Level (mg/m3) |
E-A14a |
74.4 |
54.5
– 85.8 |
197.3 |
260 |
Table 5.2 Summary of 1-hour TSP Monitoring Result in the Reporting Period
ID |
Average (mg/m3) |
Range (mg/m3) |
Action Level (mg/m3) |
Limit Level (mg/m3) |
E-A14a |
55.3 |
52.4
– 63.3 |
302.4 |
500 |
Table 5.3 Summary of Construction Noise Monitoring Results in the Reporting Period
ID |
Range, dB(A), Leq (30 mins) |
Limit Level, dB(A), Leq (30 mins) |
E-N12a |
60.2
– 67.0 |
75 |
E-N21a |
59.7
– 68.7 |
75 |
Table 6.1 Observations and Recommendations of Site Audit
Parameters |
Date |
Observations and Recommendations |
Follow-up |
Air Quality |
4 December 2020 |
· More than 20 bags of cement were observed without proper
cover at Covered Walkway. The Contractor was reminded
to provide proper cover for cement bags storage. |
The item was rectified by the
Contractor on 8 December 2020. |
· Exposed area near the cut & cover tunnel was observed
to be dry at Kai Tak. The Contractor was reminded to provide water spraying
on exposed area. |
The item was rectified by the
Contractor on 8 December 2020. |
||
Reminder: · The Contractor was reminded to replace the improper NRMM
label on the excavator at Underpass. |
The item was rectified by the
Contractor on 14 December 2020. |
||
9 December 2020 |
Reminder: · The Contractor was reminded to replace the decolored NRMM label on the excavator at Ma Tau Kok. |
The item was rectified by the
Contractor on 10 December 2020. |
|
30 December 2020 |
· Haul road was observed to be dry at Kai Tak. The
Contractor was reminded to provide regular watering on the haul road for dust
suppression. |
The item was rectified by the
Contractor on 5 January 2021. |
|
Noise |
Nil |
Nil |
Nil |
Water Quality |
9 December 2020 |
· Earth bunding was not observed along the edge of site
boundary at Covered Walkway. The Contractor was advised to provide the
bunding along the site boundary to prevent muddy water seepage. |
The item was rectified by the
Contractor on 11 December 2020. |
Waste/ Chemical Management |
9 December 2020 |
· Chemicals were observed stored without a drip tray at UWT
area. The Contractor was reminded to provide proper handling for chemical
storage. |
The item was rectified by the
Contractor on 10 December 2020. |
· General refuse was not stored in the proper receptacles
for temporary storage at C&C tunnel. The
Contractor was reminded to provide proper handling for general refuse. |
The item was rectified by the
Contractor on 15 December 2020. |
||
16 December 2020 |
· Chemicals were observed stored without drip tray at Cut
& Cover Tunnel in Kai Tak. The Contractor was reminded to provide drip
tray with sufficient storage area to prevent accidental spillage |
The item was rectified by the
Contractor on 21 December 2020. |
|
30 December 2020 |
· Chemicals were observed without drip tray at Underwater
tunnel. The Contractor was reminded to provide a drip tray for chemical
storage. |
The item was rectified by the
Contractor on 4 January 2021. |
|
· Accumulated waste was observed at the designated
receptacle at Kai Tak. The Contractor was reminded to remove the general
refuse regularly. |
The item was rectified by the
Contractor on 5 January 2021. |
||
Landscape & Visual |
Nil |
Nil |
Nil |
Permits/ Licenses |
Nil |
Nil |
Nil |
Table 8.1 Construction Activities in the coming three months
Locations |
Site Activities |
Kai
Tak |
·
Base slab and wall, roof slab construction at cut &
cover, underpass and depressed road; ·
Backfilling works and ELS removal at cut & cover,
underpass and depressed road; ·
Dismantle of working platform. |
Ma
Tau Kok |
·
TTM implementation; ·
Pipe piling works for cut and cover tunnel east portion; ·
Fresh water pipe installation works; ·
Constrcution of traffic deck; ·
Demolition of Kowloon City Public Pier. |
Kowloon
Bay |
·
Backfilling and ELS removal works; ·
Roof slab, base slab and wall construction; ·
Waterproofing application; ·
Preparation works for Stage 2 UWT. |
Barging
Point |
·
Barging point operation (Spoil Disposal); ·
Demolition of Kai Tak Barging Point1. |
Remark: 1. Kai Tak Barging Point will be handed over to other parties
at the end of February 2021. |